The ICC Arbitration Rules 2026: What They Mean for Energy, Infrastructure and Construction Disputes
The ICC has revised its Arbitration Rules and these new rules will be in effect from 1 June 2026 (2026 Rules). The new rules represent a decisive move towards earlier case crystallisation, faster outcomes, and stronger procedural discipline. The ICC explains that “[t]he revisions aim to enhance efficiency, clarity and usability.”
The energy, infrastructure and construction sectors are characterised by high‑value, long‑term projects, multiparty contractual structures, sovereign or quasi‑sovereign involvement, and disputes that can turn on discrete technical and legal issues. The 2026 Rules update will directly affect ICC disputes in these sectors.
The main changes are set out below as well as the practical implications of the new rules.
The abolition of mandatory Terms of Reference (ToR) is one of the most significant reforms. Historically, the ICC ToR were important when not all jurisdictions allowed pre-dispute arbitration agreements, and they also assisted in defining the scope of the issues early particularly in complex arbitrations. However, arguably, they often duplicated pleadings, delayed early momentum, and became a forum for tactical positioning.
This change reflects a reality already familiar for many in practice under other arbitration rules: disputes administered under LCIA and SIAC rules, for example have long proceeded without formal ToR. Indeed, the ICC’s own Expedited Procedure (which has been in operation since 2017) has functioned effectively without ToR, including in technically complex disputes.
The previous ICC Rules also prohibited the introduction of new claims after the ToR without prior permission from the Tribunal. The first case management conference now replaces the ToR as the procedural anchor and under the 2026 Rules, new claims cannot be introduced after the initial CMC without prior permission from the Tribunal (Article 25 of the 2026 Rules).
The 2026 Rules introduce an express early determination mechanism, which may be useful in avoiding unnecessary hearings and full evidentiary processes where claims or defences appear to be without merit or unsustainable. Importantly for clients, this could save time and cost and help to keep issues focussed. This mechanism may be particularly powerful to knock‑out jurisdictional objections, deal with time-barred claims efficiently, or to determine discrete contractual interpretation issues.
Despite widespread adoption of this rule by other arbitral institutions, in practice it is used cautiously and relatively sparingly. Concerns over due process, and arguments that early determination could limit one or other of the parties from having a full opportunity to present their case, can lead Tribunals to be reluctant to issue early determinations for fear of challenges to awards or allegations of procedural unfairness.
The 2026 Rules introduce a new “highly” expedited ICC procedure, with awards envisaged within approximately three months. The intention is to provide swift resolution for time-sensitive disputes with lower complexity. Practically speaking, the procedure could be documents-only without hearings or witness examination and the parties can agree to an award without reasons.
In energy and construction practice, value is often a misleading proxy for complexity; however there can also be disputes concerning discrete issues – for example payment, milestone or completion certificates, tariff or price‑adjustments, valuation provisions – which may be well suited to a “highly” expedited procedure. This may offer a credible arbitration alternative to adjudication‑style or expert determination processes for discrete disputes, which could be attractive in energy and construction projects, where commercial certainty and speed are valuable. Parties should carefully consider whether this is appropriate for their dispute.
Comparable existing procedures include SIAC’s Streamlined Procedure, which has been used in energy and commodities disputes, and certain FIDIC‑based disputes which are subject to fast‑track mechanisms before a Dispute Avoidance and Adjudication Board before escalation.
The monetary threshold for the automatic application of the Expedited Procedure has been increased to USD 4 million, potentially capturing more claims.
Practically speaking, a broader category of disputes, particularly subcontractor and discrete project claims, will now fall within expedited procedures by default. Parties must actively consider whether to opt out for complex disputes, or rely on expedited procedures as a cost-control mechanism.
For project-heavy sectors, this reinforces the importance of arbitration clause design at contract stage.
The 2026 Rules introduce a new obligation on parties to submit a list of relevant entities and individuals that arbitrators should consider for conflict purposes, at the outset, effectively front‑loading the conflict‑checking exercise and broadening the information base available to tribunals.
From a practical perspective, these changes shift conflict management to the earlier stages of proceedings, increasing initial compliance burdens but significantly reducing the scope for late-stage arbitrator challenges and tactical disruption. This is particularly significant in complex, multi‑party and state‑linked disputes, where corporate structures and repeat appointments have historically generated satellite disputes on independence.
The enhanced framework should improve predictability and procedural stability while aligning ICC practice more closely with the heightened disclosure expectations seen in ICSID and UNCITRAL contexts.
Electronic communications are now the formal default under the 2026 Rules, reflecting what is already standard in cross‑border energy and infrastructure arbitrations and large multi‑jurisdictional document‑heavy cases.
Although for many this change is largely confirmatory rather than disruptive, it reinforces the need for strong cyber‑security and data governance in sensitive projects.
The practical impact for clients is that it reinforces the need for robust document management, cybersecurity controls, and effective handling of large-scale technical evidence.
Conclusion: A Front‑Loaded, Discipline‑Driven Framework
The new ICC 2026 Rules occupy a clear middle ground: they continue the ICC’s traditional approach, which is used often in large, complex disputes, but strip out the ToR which often led to delays and introduce procedural tools previously seen in other arbitration rules, such as LCIA and SIAC, and which are already widely used in energy and infrastructure disputes.
The strategic implications are clear:
The 2026 Rules should help to make ICC arbitrations more efficient, and could reward parties who treat arbitration as a disciplined, front-loaded process.