What is CCS and what is the current environment for CCS projects?
Introduction
Carbon Capture and Storage (CCS) technology is not new – experiments first started in the 1930s – but it has recently become a key discussion point in the energy transition as stakeholders recognise its potential value in mitigating the effects of greenhouse gases on the environment.
However, it is not without its controversy since some see its role as a mitigator of fossil fuel use as being a distraction from reaching Net Zero goals.
As a newly developing technology, and one which must be scaled significantly if it is make a meaningful impact on mitigating emissions, the ability of the CCS sector to grow will be impacted by policy decisions and regulatory actions taken in individual countries, each of which currently takes different approaches. That divergence of approach is likely to continue, and to provide both opportunities and legal risks to the development of large-scale projects. In that environment, the potential for disputes is a key legal risk for participants in the sector.
In a series of two articles, we look at those legal risks and the potential disputes that may arise in the sector. This first article in the series focusses on the basics of CCS technology: what is CCS and what are some of the key policy and regulatory underpinnings of the sector at the moment? In a subsequent article, we will look at the potential disputes and key legal risks arising from this background.
Background
What is Carbon Capture and Storage?
CCS is a process that captures CO2 emissions from industrial sources such as power plants and factories, preventing them from entering the atmosphere, and then stores the CO2 underground.
CCS involves three distinct operations: (i) capture of CO2, (ii) transportation of CO2 by pipe, sea or land transport, and (iii) long-term storage under land or sea.
Carbon Capture, Utilisation and Storage (CCUS) is a subset of CCS. CCS focuses on capturing and permanently storing the CO2, whereas CCUS expands on this by finding practical applications for the captured CO2 before or instead of storage. Put simply, Carbon Capture and Utilisation (CCU) technology focuses on finding new and lucrative uses for that carbon.
Recent developments
Although CCS is not a source of renewable energy, it provides a means of mitigating emissions from fossil fuels, and as such it is reasonable to anticipate the continued use of CCS and related technologies in the years to come. The International Energy Agency (IEA) reported that as of the first quarter of 2025, there was just over 50 million tonnes (Mt) of CO2 capture and storage capacity in operation, slightly higher than one year earlier. By 2030, capture capacity is set to reach around 430 Mt CO2 per year based on the current pipeline of projects.
Power generation is the largest carbon emitter in the energy sector, creating 40% of global energy-related emissions. This statistic is unlikely to improve quickly, given the continuous increase in demand for electricity. While the global power sector must meet rising demand, it must also reduce its carbon emissions due to statutory requirements and public pressure.
Carbon capture technologies remain important because they can mitigate emissions from power plants fuelled by coal and gas where other decarbonisation options remain limited or costly, assisting in the drive to meet Net Zero goals. Notably, China and the Middle East continue to strengthen their CCUS commitments with the IEA reporting that these regions have a combined capture capacity of over 15 million tonnes of CO2 per year currently under construction.
The United Kingdom
The UK government has made a financial commitment to developing CCUS projects in a structured way through 7 proposed industrial “clusters”. The first phase of cluster deployment in 2021 led to the development of HyNet in the North West of England and North Wales, and the East Coast Cluster (ECC), in Teesside and the Humber. Towards the end of 2024, a £21.7 million commitment was made by the government to future CCUS projects. This has been swiftly followed by financial close being reached for both of the first cluster developments.
Two major carbon capture projects in Flintshire (North Wales) and Cheshire (North West England) have moved from planning stage to construction. One will be based at a cement plant in Flintshire and the other at a waste-to-energy facility in Cheshire.
The Net Zero Teesside Power (NZT Power) and the Northern Endurance Partnership (NEP) are scheduled to be the UK’s first carbon capture mega-projects in the ECC. It is expected that the projects will begin commercial operations in 2027. These two projects will form a two-part system, with NZT Power being a natural gas power station in Yorkshire that will capture CO2, and NEP providing the transport and storage system.
NZT Power and NEP have selected contractors for engineering, procurement, and construction contracts with a combined value of around £4bn.
More recently, the North Sea Transition Authority (NSTA) in the UK opened a second carbon storage licensing round, offering 14 locations offshore Scotland and England for exploration and appraisal, with the stores offering up to 2 gigatons of additional CO2 storage capacity.
In Scotland, the future for carbon capture and storage appears uncertain. The Acorn project at Peterhead in Aberdeenshire is at risk of collapse after its main backer (Storegga) announced plans to withdraw from the scheme. This is especially significant as Acorn is Scotland’s flagship carbon capture project. The project is backed by Shell UK and Harbour Energy, both of which have recently moved to scale back their involvement in UK waters. Aside from funding, two key industrial sites in Scotland have been lost, and technical problems in potential storage fields are all identified as stumbling blocks.
The Middle East
In the UAE, a number of leaders have recognised that carbon capture, utilisation, and sequestration efforts will play an important role in their goal of achieving net-zero CO2 emissions by 2050. For example, the Al Reydah CCUS project in Abu Dhabi is an integrated commercial-scale project which captures CO2 from the flue gas of an Emirates Steel production facility and injects the CO2 for enhanced oil recovery in the Abu Dhabi National Oil Company’s nearby oil fields. The project, commissioned in 2016, was reported to cost USD 122 million to set up, and aims to capture 0.8 million tonnes of CO2 (Mt CO2) per year, according to company statements.
Europe
The Carbon Border Adjustment Mechanism was fully implemented by the EU in 2026 (and is due to be implemented in the UK on 1 January 2027), bringing increased pressure to prevent carbon leakage. The Dutch Portos scheme is set to become operational in 2026, transporting around 2.5 million tonnes of C02 from Rotterdam port to depleted North sea gas fields, and Norway’s Northern Lights project saw the first CO2 stored in August 2025, and is set to open to commercial users in 2026.
Moreover, Germany plans to move from a focus on hydrogen to decarbonise industry, with CCS now on the menu as the new government pushes forward with gas-fired power plans. The German parliament recently adopted a reform allowing carbon storage under the seabed, enabling pipelines to transport CO2 and prohibiting coal power plants from using CCS. Germany’s climate neutrality targets by 2045 and net negative emissions by 2050 require technologies to capture, transport, and permanently store carbon dioxide deep underground.
Conclusion
The global landscape for CCS is rapidly evolving, and a combination of robust regulation, strategic investment and innovation is essential to drive meaningful progress. The momentum seen in policies and projects signals that CCS is being deployed to help meet ambitious climate targets and shape a low-carbon future. But what are the key legal risks for participants in the sector? Our next article in this series will look at the legal risks and potential for disputes in the CCS sector, particularly as it grows and more projects move into construction and operation.
To understand how these risks are shaped in practice, it is also useful to consider how different jurisdictions are approaching the regulation and support of CCUS. Below, we provide a brief comparison of key legal and policy frameworks across major regions.
Comparison of different jurisdictions’ approaches & regulatory issues
The successful deployment of CCUS relies on the proper establishment of legal and regulatory frameworks to ensure the effective of stewardship of CCUS activities and the safe and secure storage of CO2. The IEA CCUS legal and regulatory database provides examples of legislative approaches to CCUS from across the world. This provides a helpful database as it is organised by priority of issues that frameworks should address for CCUS development. Here, we summarise some of the variety of approaches being taken across the world.
In May 2025, the Federal Decree-Law No. (11) of 2024 on the Reduction of Climate Change Effects became effective in the UAE. The objective of this legislation was to manage emissions within the Emirates, support innovation and utilise modern technology. Article 4 of the legislation lists the ways in which emissions can be reduced to achieve climate neutrality. Article 4 (4) lists CCUS as a mitigation mechanism of climate change. This legislation is particularly significant as it includes incentives and imposes financial penalties on non-compliant companies operating onshore and within the freezones.
The UAE Ministry of Climate Change and Environment plays an important role in overseeing compliance of the obligations set out by the law. This legislation affords the Ministry the opportunity to issue resolutions regarding the controls, standards and requirements for the application of any of the means set forth in Article 4.
Article 10 details the incentives and carbon offsetting mechanisms. Article 10 (2) states as follows:
“The Ministry shall, in coordination with the entity concerned and the competent authority, adopt indicators for measuring climate performance upon studying project feasibility, with the aim of measuring the amount of emissions generated by the project during the construction and operation phases and the project’s efficiency in adapting to climate change.”
Article 10 is particularly crucial as it introduces incentives that support technological advancements that aim to facilitate the reduction of emissions.
Additionally, Article 15 introduces penalties for failure to comply with the strict climate obligations. Specifically, non-compliance may result in a fine of between AED 50,000 and AED 2,000,000.
The United States (US) is often described as the leading jurisdiction in offering generous incentives and subsides to CCUS investors. The federal section 45Q tax credit provides performance-based tax credit for carbon management projects which capture CO2. Under the Inflation Reduction Act 2022, investors could access credits of USD $85 per ton of CO2 permanently stored from stationary pollution sources and credits ranging from US$ 50 to US$ 180 per ton of CO2 removed via direct air capture (DAC). More recently, the US government has reaffirmed its support for CCS by preserving (and in some cases increasing) the federal Section 45Q tax credit in the “One Big Beautiful Bill Act” signed into law by President Trump on 4 July 2025.
The Global CCS Institute welcomed the US’s continued support, recognising the 45Q tax credit as a cornerstone policy crucial for accelerating deployment across the country. Essentially, the bill maintains the 45Q tax credit for point-source capture at US$ 85 per ton and DAC at US$ 180 per ton in dedicated geologic storage.
In the United Kingdom, similar initiatives have been introduced such as the UK’s CCS Infrastructure Fund (CIF). The fund aims to support capital expenditure on transport and storage (T&S) networks and industrial carbon capture (ICC) projects.
The CIF was first announced at Budget in March 2020, and its allocation of £1 billion was confirmed at the Spending Review in November 2020. £20 million of government funding has been invested in CCUS projects through the CCUS Innovation 2.0 programme. The UK aims to capture and store 20-30 MMt/y CO2 by 2030, backed by GBP20 billion ($25 billion) funding, rising to over 50 MMt/y by 2035. Additionally, the UK aims to establish CCUS in four industrial clusters by 2030, creating ‘SuperPlaces’ in areas such as the North East, the Humber, North West, Scotland and Wales.
In July 2025, the Netherlands and the UK agreed a Memorandum of Understanding (MoU) to establish a framework for mutually beneficial cooperation in the areas of global clean energy transition and energy security.
CCUS had been identified as a priority area for development under the MoU and the UK and the Netherlands aim to collaborate and cooperate on the development and deployment of CCUS. This includes on issues such as regulatory and technical development, knowledge sharing, and the cross-border transport and storage of CO2.
Oil and gas majors are also looking to expand their CCS projects, with ExxonMobil being the market leader by some distance. Exxon has a total of 25 mtpa of capture capacity spread across its portfolio, both operational facilities and those in the pipeline. More recently, it was reported that five suitors have submitted non-binding bids for a minority stake in Eni SpA’s CCS business.